84th Ave over I-25 Bridge Replacement
|
Replace the existing structure that was originally built in 1959. The new bridge will be wider to accommodate an additional turn lane from eastbound 84th Ave to northbound I-25. In addition there will be 10-foot wide sidewalks on each side of the bridge to improve pedestrian and bicycle safety.
Location: Thornton, CO |
![]() ![]() ![]() ![]() ![]() see below to scroll through photos & enlarge
|
Project Updates:
Look ahead to May 4th:
Zak Dirt is continuing to work on the final phase of the 84th Avenue Bridge. Crews are preparing to place the concrete deck scheduled for the end of April. Along with the structure work, crews are beginning to construct the southern roadway portion of 84th Avenue, which will include new paving and sidewalks. Motorists will also see the addition of concrete retaining walls underneath the bridge which will allow for future expansion of I-25. Please use caution while traveling through the site as traffic alignments change frequently.
Updated By: admin
Look ahead to February 28th:
Zak Dirt is getting ready to begin the last phase of bridge workon the 84th Ave Project. I-25 will be shutdown on Feb. 7th and 8th from 10:30 P.M. -5:30 A.M. for bridge removal. Crews will continue to work throughout the month on the final phase of the bridge as well as improvements to the roadway. Please use caution when traveling through the work zone as conditions change frequently.
Updated By: admin
Look ahead to December 19th - January 13th:
Zak Crews successfully completed the Phase II Bridge deck. In the coming weeks, crews will complete the approaches to the new bridge. East bound traffic on 84th is scheduled to be moved onto the new structure in mid January. Once traffic is switched over, Zak will begin work on the last phase of the project. Please use caution while traveling through the work zone, as traffic alignments change frequently.
Updated By: admin
This is our current forecast; please click here for the most current updates.
-
Click to enlarge
84th Avenue Monuments
1/31/2012
-
Click to enlarge
Wall at 84th Avenue
11/14/2011
-
Click to enlarge
84th Ave over I-25 Deck Pour
9/6/2011
-
Click to enlarge
84th Ave over I-25 Bridge Deck Rebar
9/6/2011
-
Click to enlarge
Crews working on Bridge Deck at 84th Avenue over I-25
8/19/2011
-
Click to enlarge
Crews working on Coping Overhang on 84th Avenue Bridge over I-25
8/19/2011
-
Click to enlarge
Bridge Girder Placement, 84th Avenue over I25 Phase I
8/8/2011
-
Click to enlarge
Crane Setting Bridge Girders, 84th Avenue over I25 Phase I
8/8/2011
-
Click to enlarge
Substructure - 84th Avenue over I25 Bridge Replacement
7/22/2011
-
Click to enlarge
MSE Wall at 84th Avenue and I-25
7/22/2011
-
Click to enlarge
84th Avenue over I25 Bridge Demolition
6/9/2011
-
Click to enlarge
84th Avenue over I25 Bridge Demolition
6/7/2011
-
Click to enlarge
84th Avenue over I25 Bridge Demolition
6/7/2011
-
Click to enlarge
Bridge to be replaced
4/27/2011